Island Structure
The most difficult task was the planning of the construction of the new decant structure and outfall pipe. This structure consisted of installing 16, 8-foot long, steel pipe piles, the installation of 2,
40-cubic yard concrete pile caps, the construction of a 25-foot tall decant structure, the installation of 1,500 feet of 60-inch inside diameter, high density polyethylene pipe and the installation of 3 large, pre-cast concrete junction boxes. The decant structure itself was designed as part of a value engineering option in the WRScompass contract with the TPA.
The overall cost savings to the TPA was approximately $850,000. By far, the most logistically challenging part of this project was the transportation of concrete to the island for the construction of the pile caps supporting the decant structure. The concrete mix design constraints and transportation time to the island presented WRScompass with an extremely short window for completing this task. This task was completed in 2 days, with the first pile cap installed on the first day and the second cap poured the following week. This concrete pour exceeded the largest remote pour performed for TPA activities to date.
American Oyster Catcher Habitat
The American Oyster Catcher is one of the top ten listed “At Risk” species that the Audubon Society is focusing on. The new habitat was constructed as part of a study performed by the Regional Audubon Society. WRScompass was instrumental in locating and increasing the size of the habitat according to a design completed by a joint/team effort between WRScompass, Tampa Port Authority, the Audubon Society, and the Florida DEP. These habitats are large sea-side rip-rap groins placed in shallow water, and aid in the protection of sensitive nesting areas that have been historically damaged by waves generated from large sea-going vessels.